Building Future: Referendum Progress
Coming Soon: Full-Day Kindergarten 2022-23
Ground Breaking
On May 17, 2021, the D34 Board of Education, Village Representatives, administrators and students broke ground at Lyon, Westbrook and Henking elementary schools and Springman Middle School.
An Overview
On March 17, 2020, the community approved a referendum for $119 million to allow District 34 to repair, replace and update our buildings.
This successful referendum signals that residents understand the importance of reinvesting in the school district’s capital assets. The impact of the referendum will positively impact the community for decades to come, and it will be felt at every school, in every classroom, by every District 34 student. We recognize that we are tasked with Building Future.
School Construction Schedule
Westbrook Timeline
- Week of 6/7/21 - 6/11/21
- Week of 6/14/21 - 6/18/21
- Week of 6/21/21 - 6/25/21
- Week of 6/28/21 - 7/2/21
- Week of 7/5/21 - 7/9/21
- Week of 7/12/21 -7/17/21
- Week of 7/19/21 - 7/24/21
- Week of 7/26/21 - 7/31/21
- Week of 8/2/21 - 8/7/21
- Week of 8/9/21 - 8/14/21
- Week of 8/16/21 - 8/21/21
- Week of 12/13/21 - 12/18/21
- Week of 8/23/21 - 8/28/21
- Week of 8/30/21 - 9/4/21
- Week of 9/6/21 - 9/11/21
- Week of 9/13/21 - 9/18/21
- Week of 9/20/21 - 9/25/21
- Week of 9/27/21 - 10/2/21
- Week of 10/4/21 - 10/9/21
- Week of 10/11/21 - 10/16/21
- Week of 10/18/21 - 10/23/21
- Week of 10/25/21 - 10/30/21
- Week of 11/1/21 - 11/6/21
- Week of 11/8/21 - 11/13/21
- Week of 11/15/21 - 11/20/21
- Week of 11/22/21 and 11/29/21
- Week of 12/6/21 - 12/11/21
- Week of 1/10/22 - 1/15/22
- Week of 1/17/22 - 1/22/22
- Week of 1/24/22 - 1/29/22
- Week of 1/31/22 & 2/7/22
- Week of 2/7/22 - 2/12/22
- Week of 2/14/22 & 2/21/22
- Week of 2/28/22 - 3/5/22
- Week of 3/7/22 & 3/15/22
- Week of 3/21/22 - 3/26/22
- Week of 3/28/22 & 4/4/22
- Week of 4/4/22 - 4/9/22
- Week of 4/11/22 - 4/16/22
- Week of 4/18/22 -4/23/22
- Week of 4/25/22 & 5/2/22
- Week of 5/2/22 - 5/7/22
- Week of 5/9/22 & 5/16/22
- Week of 5/16/22 - 5/21/22
- Week of 5/23/22 - 5/28/22
- Week of 5/31/22 - 6/4/22
- Week of 6/6/22 - 6/11/22
Week of 6/7/21 - 6/11/21
Week of 6/14/21 - 6/18/21
Week of 6/21/21 - 6/25/21
Riemer
- Construction entrances
- Temp access roads
- Jobsite trailer
- Excavate for footings
- Excavate for storm trap
- Grade south playground area
- Tree removal at north property line
American
- Temp power to trailer
Eagle
- Frame/Reinforce/Pour (F/R/P)
Johler
- Demo existing canopy (partial), overhangs, and interior Classroom 41
Week of 6/28/21 - 7/2/21
Week of 7/5/21 - 7/9/21
Week of 7/12/21 -7/17/21
Week of 7/19/21 - 7/24/21
Riemer
- Excavate for footings
- Cut and fill for building
- Install sidewalks and curbs at playground area
Eagle
- Frame/Reinforce/Pour (F/R/P) footings and foundation walls
- Complete base slab for storm trap
- F/R/P stoop at door 41A
Mastership
- Tooth door opening 41A
Monarch Construction
- Complete footing demolition at south end B-wing
DeKalb Mechanical
- Reroute mechanical piping/reinstall CUV in classroom 41
American
- Power to construction trailer
Week of 7/26/21 - 7/31/21
Riemer
- Backfill footings
- Continue site grading
- Stone access for P/C erection
Siebert
- Landscape and surface install at playground
Action Fencing
- Install fence north property line
Spancrete
- Install deadmen for P/C installation
Eagle
- Frame/Reinforce/Pour (F/R/P) footings and foundation walls
Madden Glass
- Install door 41A
Week of 8/2/21 - 8/7/21
Riemer
- Complete playground install
- Backfill foundations
Siebert
- Landscape and surface install at playground
Eagle
- Frame/Reinforce/Pour (F/R/P) footings and walls
Spancrete
- Install P/C panels and planks
Monarch Construction
- Demo east canopy following removal of fluid coolers
Jensen's
- Start UG plumbing after install of P/C
DeKalb Mechanical
- Prepare existing piping for temporary chiller
American Electrical
- Prepare existing infrastructure for temporary chiller
Week of 8/9/21 - 8/14/21
Riemer
- Backfill foundations
- Backfill stormtrap
- Stone for parking on east side
Siebert
- Landscape install at playground
AJ Oleson
- Stormtrap installation
- Storm lines to/from stormtrap
Eagle
- Complete Frame/Reinforce/Pour (F/R/P) footings and walls
- Install shallow footings at MPC
- Prepare MPC roof deck for 6" topping placement
Mastership
- Tooth in around door opening 41A
Mobile Air
- Deliver temporary cooling tower
Monarch
- Install temporary door 41A
Jensen's
- UG plumbing
DeKalb Mechanical
- install valves/couplings for temporary cooling tower
- Demo air cooled chiller
American Electrical
- Install power requirements for temporary cooling tower
- Cut power to existing air cooled chiller
- Underslab rough-in at MPC area
Week of 8/16/21 - 8/21/21
Riemer
- Excavate for footings at A, 9, E and at canopy
- Backfill stormtrap
AJ Oleson
- Backfill perimeter of stormtrap
- Storm lines to/from stormtrap
Eagle
- F/R/P footings and walls
- Install shallow footings at MPC
- Place 6" topping placement at MPC roof
Mobile Air
- Temporary cooling tower start-up
Monarch
- Demo canopy
Jensen's
- UG plumbing
DeKalb Mechanical
- Demo existing fluid coolers
American Electrical
- Cut power to existing fluid coolers
- Underslab rough-in
Week of 12/13/21 - 12/18/21
Mastership
- Brick installation on Areas A & B walls
Monarch
- Install HM frames
Elens & Maichin
- Roofing
RB Construction
- Interior partition/soffit/ceiling installations
- Interior drywall installation
- Install Tectum Ceiling Panels in MPR
Madden Glass
- Windows in Area B (Week of 12/20/2021)
Nelson Fire Protection
- Above grade rough-in
Jensen’s
- Above grade rough-in
DeKalb Mechanical
- Above grade rough-in
- Set RTU1, MAU, PCU & DOAS
American Electrical
- Above grade rough-in
Week of 8/23/21 - 8/28/21
Riemer
- Final grade site
- Backfill foundations as required
- Stone building pad as required
AJ Oleson
- Storm lines to/from stormtrap, sanitary line, water lines
Eagle
- Place 6" topping slab on precast roof deck
- Complete F/R/P footings and walls
Spancrete
- Pull braces and deadman that interfere with other work
Mastership
- Start CMU load bearing walls
Monarch
- Complete canopy demo
Jensen's
- UG plumbing
American Electrical
- Underslab rough-in
Week of 8/30/21 - 9/4/21
Riemer
- Final grade site
- Backfill foundation as required
Oleson
- Storm lines to/from stormtrap, sanitary line, water lines
Mastership
- CMU load bearing walls along existing building
M&I Steel
- Begin structural steel installation
Elens & Maichin
- Temp patch existing roof
Jensen's
- UG plumbing
American Electrical
- Underslab rough-in
Week of 9/6/21 - 9/11/21
Week of 9/13/21 - 9/18/21
Week of 9/20/21 - 9/25/21
Riemer
- Final grade for SOB P to X/1 to 7 (Friday 9/24)
Eagle
- Prep SOG to X/1 to 7 (Friday 9/24)
M&I Steel
- Structural steel installation north of P line (Monday thru Friday)
- Install metal roof decking south of P line (Monday thru Wednesday)
- Complete mezzanine steel/decking
Mastership
- Complete CMU walls in MPR (Monday thru Friday)
Elans & Maichin
- Check moisture requirements at MPR roof
- Mobilization for roofing P to X/1 to 7
RB Construction
- Layout for exterior wall installation (Thursday thru Friday)
- Begin installation of exterior walls (Thursday thru Friday)
Jensen's
- Prep P to X/1 to 7 for SOG placement (Wednesday, Thursday)
- Underground rough-in small addition end of B Wing (Monday - Wednesday)
DeKalb Mechanical
- On-site to coordinate opening in CMU walls at MPR with Mastership
American Electrical
- Underground rough-in P to X/1 to 7 (Wednesday, Thursday)
Week of 9/27/21 - 10/2/21
Riemer
- Finish grade SOG Area B (M)
- Backfill MPR bathrooms and finish grade MPR SOG
Eagle
- Prep/pour SOG Area B (T/W/Th)
- Prep/pour mezz deck
Oleson
- 24" (RFP-007WB) & RFP-014WB
M&I Steel
- Steel Delivery (M)
- Structural Steel North/East of MPR
Elans & Maichin
- Roof prep/install - Area B
- Test concrete topping on MPR
Jensen's
- UG plumbing at roof vents
American Electrical
- Underslab rough-in
RB Construction
- Exterior CFMF framing
- Interior wall layout
Week of 10/4/21 - 10/9/21
Riemer
- Final grade site & SOG
Oleson
- 24" (RFP-007WB) & RFP-014WB
Eagle
- Prep/pour SOG Area B & MPR
M&I Steel
- Structural Steel North/East of MPR
Jensen's
- In wall rough and roof vents
American Electrical
- In wall rough and roof vents
DeKalb
- Ductwork and in wall rough
RB Construction
- Exterior CFMF framing
- Interior wall layout
Elens & Maichin
- Roof prep/install Area B/MPR
Week of 10/11/21 - 10/16/21
Riemer
- Finish grade site & SOG
Eagle
- Prep/pour SOG MPR (Monday 10/11 to Tuesday 10/12)
Mastership
- CMU walls for rooms A121. A122, A123, A124 (Thursday 10/14 to Friday 10/15)
M&I Steel
- Complete structural steel/decking installation
Elens & Maichin
- Roofing
RB Construction
- Exterior wall Installation
- Install air/vapor barrier B-wing walls
- Install perimeter rigid insulation B-wing walls
Nelson Fire Protection
- Above grade rough-in
Jensen's
- Above and below grade (kitchen) rough-in
DeKalb Mechanical
- Above grade rough-in
American Electric
- Above and below grade rough-in
Week of 10/18/21 - 10/23/21
Riemer
- Final grade for SOG E to N/9 to 11, K to P/4 to 9, D to P/1 to 4 (Tuesday)
- Final grade site
Eagle
- Prep/pour SOG E to N/9 to 11, K to P/4 to 9, D to P/1 to 4 (Wednesday, Thursday)
Mastership
- Begin brick installation on Area B walls
Elens & Maichin
- Roofing - Area B wing and MPR
RB Construction
- Exterior wall installation (Area A, roofing transitions, Area B)
- Install air/vapor barrier Area B walls
- Install perimeter rigid insulation Area B walls
Nelson Fire Protection
- Above grade rough-in
Jensen's
- Above grade rough-in in Area B
- Underground work in kitchen
DeKalb Mechanical
- Above grade rough-in
- Set DOAS curb
American Electrical
- Above and below grade rough-in
Week of 10/25/21 - 10/30/21
Riemer
- Final grade site
- Proof roll/stone all drives/ parking pads
Eagle
- Place SOG D to P/1 to 4
Mastership
- Brick installation on Area B walls
M&I Steel
- Install stair to mechanical mezzanine
Monarch
- Install door frames Area B
- Board up exterior openings
Elens & Maichin
- Roofing - complete MPR, east and south sides MPR
RB Construction
- Exterior wall installation
- Interior partition installation
Nelson Fire Protection
- Above grade rough-in
Jensen's
- Above grade rough-in
- Kitchen underground
DeKalb Mechanical
- Above grade rough-in
American Electric
- Above grade rough-in
Week of 11/1/21 - 11/6/21
Eagle
- Prep/pour SOG A to D/1 to 4, kitchen area (freezer/cooler base)
Mastership
- Brick installation on Area B walls
Monarch
- Install door frames Area B
- Board up exterior openings
Elens & Maichin
- Roofing
RB Construction
- Exterior wall installation
- Interior partition installation
Nelson Fire Protection
- Above grade rough-in
Jensen's
- Above grade rough-in
- Complete kitchen underground
DeKalb Mechanical
- Above grade rough-in
- Complete install of temp heating system
American Electric
- Above grade rough-in
Week of 11/8/21 - 11/13/21
Reimer
- Complete grading of east side and stone all drives and parking areas
AJ Oleson
- Watermain and sanitary sewer on north side
- Complete storm sewers on south side
Eagle
- Prep/Pour SOG A to D/1 to 4, Kitchen area
Elens & Maichin
- Roofing Areas W & T
Mastership
- Brick installation on Area B walls
Monarch
- Install door frames area B
- Board up exterior openings
Elens & Maichin
- Roofing
RB Construction
- Exterior Wall Installation
- Interior partition installation
Jensen’s
- Above grade rough-in
- Install grease trap
DeKalb Mechanical
- Above grade rough-in
- Complete install of temp heating system
American Electrical
- Above grade rough-in
Week of 11/15/21 - 11/20/21
Riemer
- Silt fence at stockpile
Oleson
- Set sanitary manhole C and coord. with plumber for grease trap piping
M&I Steel
- Deliver L2 lintels on Thursday
Mastership
- Brick installation Area B walls
Monarch
- Install HM frames
- Complete board-up
Elans & Maichin
- Roofing Areas X, Y (Areas available now for final roofing – V, W, Z and AA)
- Plywood backside of parapet walls currently open to below - CRITICAL
RB Construction
- Exterior Wall Installation
- Exterior soffit framing
- Interior partition installation
- Complete AVB
- Spray foam
Jensen’s
- Above grade rough-in
- Set grease trap
- Set vents at roof Areas R and S (Coordinate with Elens & Maichin)
DeKalb Mechanical
- Above grade rough-in
- Set DOAS curb at roof Area T??? (Coordinate with Elens & Maichin)
- Set exhaust curb at roof Areas R and S (Coordinate with Elens & Maichin)
American Electrical
- Above grade rough-in
- Directional bore for ComEd primaries
Week of 11/22/21 and 11/29/21
Mastership
- Brick installation on Areas A & B walls
Monarch
- Install HM frames
Elans & Maichin
- Roofing
RB Construction
- Interior partition installation
Madden Glass
- Windows in Area B (Week of 11/29/2021)???
Jensen’s
- Above grade rough-in
DeKalb Mechanical
- Above grade rough-in
American Electrical
- Above grade rough-in
Week of 12/6/21 - 12/11/21
Eagle
- Pour 3 missing pier supports
Mastership
- Brick installation Area B walls
Monarch
- Install HM frames (A101, A102, A103, A104, A105, A106, A107, A108)
- Install balance of HM borrowed lite frames in corridor 010
Elens & Maichin
- Roofing Areas T, W, Z, AA
RB Construction
- Complete exterior soffit framing with plywood sheathing
- Complete spray foam exterior overhang eaves
- Patch spray foam in exterior walls where exterior pilasters poke through
- Interior partition installation
- Start drywalling corridor 010
- Start framing soffits in corridor 10
- Start framing in kitchen (after ductwork, coordinate with plumber)
Nelson Fire Protection
- Install piping Area A (Except MPR)
Jensen’s
- Above grade rough-in
DeKalb Mechanical
- Above grade rough-in
American Electrical
- Above grade rough-in
- Directional bore for ComEd primaries
Week of 1/10/22 - 1/15/22
Elens & Maichin
- Roofing roof area Q
- Patch between existing and new roof
- Eaves/Fascia/Soffit
Madden Glass
- Window installation
Mastership
- Brick and window sill installation Area A
- Clean brick Area A
- Interior CMU at MPR
- AVB exterior CMU where abuts existing building
- Interior brickwork
M&I Steel
- Set chiller framing (Thursday/Friday)
RB Construction
- Interior drywall hanging and taping
- Misc framing for soffits/ceilings
- Layout corridor 10 ceiling
Nelson Fire Protection
- Hang sprinkler piping in MPR
- Misc rough-in as required
- Adjust piping in soffits of A111 Reading room, A125, Verify Corridor 09
Jensen’s
- Misc rough-in as required
DeKalb Mechanical
- Misc rough-in as required
American Electrical
- Misc rough-in as required
Week of 1/17/22 - 1/22/22
AJ Oleson
- Sanitary Sewer
- Water Line
Madden Glass
- Window installation
Mastership
- Misc masonry where required
RB Construction
- Interior drywall hanging and taping
- Misc framing for soffits/ceilings
- Begin painting TBD
Nelson Fire Protection
- Misc rough-in as required
Jensen’s
- Misc rough-in as required
DeKalb Mechanical
- Misc rough-in as required
American Electrical
- Misc rough-in as required
Week of 1/24/22 - 1/29/22
AJ Oleson
- Sanitary Sewer
- Water Line
Eagle
- Grind/Patch floor in Kitchen and MPR
Spancrete
- Clean saw cut paste from face of wall in MPR
Elens & Maichin
- Patch between existing and new roof (weather pending after completion of AVB)
- Eaves/Fascia/Soffit – Blocking, backing and metal
Mastership
- Clean brick Area A (weather permitting)
- Complete exterior brick (weather permitting)
- Interior CMU at MPR
- Interior brickwork
- AVB exterior CMU where abuts existing building (weather permitting)
Madden Glass
- Window installation
RB Construction
- Misc Framing
- Columns and window seats at Area B Classrooms
- Interior drywall hanging and taping
- Hang/tape drywall in main electrical room
- Corridor 10
- Outside walls Area B
- Rooms A132 and A133
- Ceilings in toilet rooms Area B
Jensen’s
- Misc rough-in as required
- Install valve tags
- Fire safe/Seal wall penetrations
DeKalb Mechanical
- Misc rough-in as required
- Fire safe/Seal wall penetrations
American Electrical
- Misc rough-in as required
- Fire safe/Seal wall penetrations
Week of 1/31/22 & 2/7/22
Madden Glass
- Window installation
Consolidated
- Toilet room finish install (Week of 1/31/22)
RB Construction
- Misc framing
- Interior drywall hanging and taping
- Painting
- Mechanical Mezz (Week of 1/31/22)
- MPR Ceiling (Week of 1/31/22)
- A109 Area
- Area B Classrooms (Week of 2/7/22)
Jensen’s
- Misc rough-in as required
- Valve extensions and tags
- Fire safe/Seal wall penetrations
DeKalb Mechanical
- Misc rough-in as required
- AMI valve extensions
- AMI control valves and piping to FCU’s
- Fire safe/Seal wall penetrations
- Install AHU-1 (week of 02/07/2022)
American Electrical
- Misc rough-in as required
- Fire safe/Seal wall penetrations
Week of 2/7/22 - 2/12/22
Spancrete
- Clean saw cut paste from face of walls in MPR
Elens & Maichin
- Patch between existing and new roof (weather pending after completion of AVB)
- Eaves/Fascia/Soffit – Blocking, backing and metal
Mastership
- Clean exterior brick Area A (weather permitting)
- Complete exterior brick (weather permitting)
- AVB exterior CMU where abuts existing building (weather permitting)
Madden Glass
- Window installation
Consolidated
- Toilet room finish install
RB Construction
- Misc framing
- Interior drywall hanging and taping
- Painting
DeKalb Mechanical
- Misc rough-in as required
- AMI valve extensions
- AMI control valves and piping to FCU’s
- Fire safe/Seal wall penetrations
- MPR louver/damper installations
- Install AHU-1
American Electrical
- Misc rough-in as required
- Fire safe/Seal wall penetrations
Week of 2/14/22 & 2/21/22
Elens & Maichin
- Eaves/Fascia/Soffit – Blocking, backing and metal
Madden Glass
- Window installation
Consolidated
- Toilet room finish install
RB Construction
- Misc framing
- Interior drywall hanging and tapingo Painting
- Install ceiling grid classrooms (week of 02/21/2022)
Nelson Fire Protection
- Trim to grid (Week of 02/21/2022)
DeKalb Mechanical
- Misc rough-in as required
- AMI valve extensions
- AMI control valves and piping to FCU’s
- Fire safe/Seal wall penetrations
- MPR louver/damper installations
- Trim to grid (Week of 02/21/2022)
American Electrical
- Misc rough-in as required
- Fire safe/Seal wall penetrations
- Trim to grid (Week of 02/21/2022)
Week of 2/28/22 - 3/5/22
AJ Oleson
- Sanitary and water installation (Weather permitting)
Elens & Maichin
- Patch between existing and new roof (weather pending after completion of AVB)
- Eaves/Fascia/Soffit – Blocking, backing and metal
Mastership
- AVB exterior CMU where abuts existing building (weather permitting)
Madden Glass
- Window installation
RB Construction
- Interior drywall hanging and taping
- Painting
- Install ceiling grid classrooms
Nelson Fire Protection
- Trim to grid
DeKalb Mechanical
- Install AHU #1
- Trim to grid
American Electrical
- Electrical Rooms
- Misc rough-in as required
- Trim to grid
Week of 3/7/22 & 3/15/22
Eagle
- Complete stoops
Elens & Maichin
- Patch between existing and new roof (weather pending after completion of AVB)
- Eaves/Fascia/Soffit – Blocking, backing and metal
Mastership
- AVB exterior CMU where abuts existing building (weather permitting)
Madden Glass
- Window installation
Monarch
- Install Hood and stainless wall panels on north wall kitchen (Week of 3/7)
Consolidated
- Epoxy flooring in toilet rooms
RB Construction
- Interior drywall hanging and taping
- Painting
- Install ceiling grid classrooms
- Install tectum wall panels in MPR (Week of 3/7)
Nelson Fire Protection
- Trim to grid
Jensen’s
- Fixture install in toilet rooms (Week of 3/15 pending completion of epoxy flooring)
DeKalb Mechanical
- Misc rough-in as required
- Fire safe/Seal wall penetrations
- Trim to grid
American Electrical
- Electrical Rooms
- Misc rough-in as required
- Trim to grid
Week of 3/21/22 - 3/26/22
AJ Oleson
- Storm, Sanitary and Watermain installation
Eagle
- Complete stoops
Elens & Maichin
- Eaves/Fascia/Soffit – Blocking, backing and metal
Madden Glass
- Exterior Door installation
Consolidated
- Mitigation (Starting 03/23/2022)
- Epoxy flooring in toilet rooms (Starting 03/25/2022)
RB Construction
- Soffit/Walls/Ceiling between new and existing buildings
- Complete ceiling grid all areas
- Taping Pre-K Classrooms
- Painting
Nelson Fire Protection
- Trim to grid
Jensen’s
- Video underground for Ph 2 work
DeKalb Mechanical
- Ductwork in mechanical mezzanine
- Complete HVAC in Pre-K
- Install radiant ceiling panels
- Remove ceiling CUH and two CUH in link between old/new buildings
American Electrical
- Electrical Rooms
- Trim to grid
- Conduit through to boiler room
- Install ComEd primary conduit
Week of 3/28/22 & 4/4/22
AJ Oleson
- Complete underground as necessary
Elens & Maichin
- Eaves/Fascia/Soffit – Blocking, backing and metal
Madden Glass
- Door installation
- SF entrance installation
Consolidated
- Epoxy flooring in toilet rooms
- Complete floor mitigation
- VCT (Week of 03/28/2022)
- Carpeting (Start 03/29/2022)
RB Construction
- Painting
- Hang balance of drywall in Pre-K
DeKalb Mechanical
- Mechanical Mezzanine
American Electrical
- Electrical Rooms
Upcoming work: Toilet Fixtures (Week of 04/04/2022)
Casework (Week of 04/11/2022)
Week of 4/4/22 - 4/9/22
AJ Oleson
- Complete underground
Eagle
- Grind floors in MPR toilet rooms
Elens & Maichin
- Eaves/Fascia/Soffit – Blocking, backing and metal
Madden Glass
- SF entrance installation
Consolidated
- Complete floor mitigation
- Carpeting in classrooms
RB Construction
- Painting
- Complete framing soffit/walls/ceiling between new and existing buildings
- Hang balance of drywall in Pre-K
- Taping Pre-K Classrooms
Jensen’s Plumbing
- Install toilet room fixtures
DeKalb Mechanical
- Mechanical Mezzanine
American Electrical
- Electrical Rooms
- Trim to grid
- Begin trim-out of voice/data cabling
Week of 4/11/22 - 4/16/22
AJ Oleson
- Complete underground as necessary
Riemer
- Site Grading
- Curbs
Elens & Maichin
- Eaves/Fascia/Soffit – Blocking, backing and metal
Madden Glass
- Door installation
- SF entrance installation
Consolidated
- Epoxy flooring in Kitchen (partial), MPR toilet rooms and janitor’s closets
- VCT
- Carpeting
RB Construction
- Painting
- Hang balance of drywall in Pre-K
DeKalb Mechanical
- Mechanical Mezzanine
American Electrical
- Electrical Rooms
- Install ComEd secondary conduit
- Install site electric east
Week of 4/18/22 -4/23/22
Riemer
- Site Grading
AJ Oleson
- Complete storm underground
Eagle
- Grind floors in MPR toilet rooms
Elens & Maichin
- Eaves/Fascia/Soffit – Blocking, backing and metal
Madden Glass
- SF entrance installation
Consolidated
- Carpeting in classrooms
- VCT in corridors
Monarch
- Casework
RB Construction
- Complete framing soffit/walls/ceiling between new and existing buildings
- Complete framing vestibule A6
- FRP in kitchen
- Hang balance of drywall in Pre‐K
- Taping Pre‐K Classrooms
Jensen’s Plumbing
- Install toilet room fixtures
- Above ceiling punch items
DeKalb Mechanical
- Trim in kitchen
- Hang duct in MPR
- Above ceiling punch items
American Electrical
- Site electrical
- Fire Alarm Trim
- Receptacle trim
- Complete audio/visual in MPR
- Above ceiling punch items
Week of 4/25/22 & 5/2/22
Riemer
- Site Grading
- Curbs
Elens & Maichin
- Eaves/Fascia/Soffit – Blocking, backing and metal
Madden Glass
- Door installation
- SF entrance installation
Consolidated
- Epoxy flooring MPR toilet rooms and janitor’s closet
- VCT
- Carpeting
- Ceramic tile in Area A and Pre‐K toilet rooms
Monarch
- Casework
- Toilet accessories and partitions
- Gym equipment
- Coiling doors in MPR
RB Construction
- Complete taping in Pre‐K
- Painting
- Ceiling tile install
- Complete ceiling grid in Area A
- Ceiling grid in Pre‐K
Nelson
- Trim to grid in Pre‐K
Jensen’s
- Install fixtures in casework
DeKalb Mechanical
- Trim to grid in Pre‐K
American Electrical
- Electrical Rooms
- Trim to grid in Pre‐K
- Site electric
Week of 5/2/22 - 5/7/22
Riemer
- Site Grading & Curbs
Elens & Maichin
- Eaves/Fascia/Soffit – Blocking, backing and metal
Madden Glass
- SF entrance installation
Consolidated
- Carpeting in classrooms
- VCT in corridors
- Ceramic tile Pre-K
Monarch
- Install wood and HM doors
RB Construction
- Complete drywall vestibule A6
- Painting in Pre-K
- Install ceiling grid Pre-K
- Install ceiling tile
DeKalb Mechanical
- Insulate ductwork Pre-K
American Electrical
- Site electrical
- Fire Alarm Trim
- Receptacle trim
- Low voltage trim
Week of 5/9/22 & 5/16/22
Riemer
- Site Grading & Curbs
Elens & Maichin
- Eaves/Fascia/Soffit – Blocking, backing and metal
Madden Glass
- Door installation
- SF entrance installation
Consolidated
- Epoxy flooring MPR toilet rooms and janitor’s closet
- VCT
- Carpeting
- Ceramic tile in Area A and Pre-K toilet rooms
Monarch
- Wood and HM doors
- Toilet accessories and partitions
- Gym equipment
- Coiling doors in MPR
RB Construction
- Painting (Interior and exterior)
- Ceiling tile install
- Complete ceiling grid
Nelson
- Trim to grid in Pre-K
Jensen’s
- Install fixtures in casework
DeKalb Mechanical
- Trim to grid in Pre-K
American Electrical
- Electrical Rooms
- Fire Alarm
- Low Voltage
- Trim to grid in Pre-K
- Site electric
Week of 5/16/22 - 5/21/22
Riemer
- Cut for curbs and drives
AJ Oleson
- Adjust frames on MH/CB’s
Eagle
- Sidewalks and curbs
Elens & Maichin
- Roof Screens
Monarch
- Install doors and hardware
- Install coiling doors
- Install basketball equipment
- Install toilet accessories
Madden Glass
- SF entrance installation
Consolidated
- Complete VCT
- Epoxy flooring in Kitchen (partial), MPR toilet rooms and janitors’ closets
RB Construction
- Paint exterior Precast
- Complete drywall ceilings
- Install ceiling tiles
- Ceramic tile install
Nelson
- Trim to grid in Pre‐K
DeKalb Mechanical
- Trim to grid in Pre‐K
American Electrical
- Trim to grid in Pre‐K
- Misc. lighting and trim out
Week of 5/23/22 - 5/28/22
Phase 1
Riemer
- Cut for drives
Eagle
- Walks and curbs
K&L
- Prep for asphalt paving
M&I
- Angles and plates at coiling door walls in MPR
Mastership
- CMU walls in MPR
Elens & Maichin
- Complete roof screens
Monarch
- Install doors and hardware Pre‐K
- Install casework in Pre‐K
Madden Glass
- Caulk and complete glazing
Consolidated
- Mitigate Pre‐K corridor
- VCT
- Carpeting
- Complete ceramic tile
RB Construction
- Painting
- Ceilings in Pre‐K
Jensen’s Plumbing
- Trim in Pre‐K
DeKalb Mechanical
- Begin demo in boiler room
American Electrical
- Misc trim
Phase 2
Monarch
- Install floor protection
- Begin demolition existing toilet room
Jensen’s Plumbing
- Demo existing toilet room
American
- Demo existing toilet room
Week of 5/31/22 - 6/4/22
Phase 1
Riemer
- Backfill curbs
- Cut roadway where required
- Proof roll
- Excavate for storm trap and door F footings
Eagle
- Walks
K&L
- Prep for asphalt paving
Mastership
- CMU walls in MPR
Elens & Maichin
- Install roof screens
Monarch
- Complete install of coiling doors
- Install interior partition at Door F
- Demo for Door F construction
Consolidated
- Mitigate Pre-K corridor and seal mezzanine concrete
- VCT
- Carpeting
- Complete ceramic tile
RB Construction
- Painting
- Complete drywall install and tape
Jensen’s Plumbing
- Misc trim
DeKalb Mechanical
- Begin demo in boiler room
American Electrical
- Misc trim
- Site work
Phase 2
Others
- Abatement
- Move classroom furniture
Monarch
- Install floor protection
- Begin demolition existing toilet room
- Begin demolition classroom wing
Jensen’s Plumbing
- Demo existing toilet room
- Layout for floor removal
Helm
- Demo
American
- Demo existing toilet room
Week of 6/6/22 - 6/11/22
Phase 1
Riemer
o Backfill curbs/respread
o Complete excavation of storm trap
Eagle
- Walks and concrete paving
- Footings at door F
- Storm trap base slab
Mastership
- CMU walls in MPR
Monarch
- Remove ceiling in corridors 03 and 04
- Final clean classrooms
- Casework Pre-K classrooms
Consolidated
- VCT MPR and Pre-K
- Carpeting
RB Construction
- Painting
Jensen’s Plumbing
- Boiler Room
DeKalb Mechanical
- Demo boiler room
American Electrical
- Misc
- Site Work
Phase 2
Monarch
- Classroom demolition
- Board-up Openings
Mastership
- Cut door openings/Infill Unit Vents
Commercial
- Demo flooring in existing building
Jensen’s Plumbing
- Demo existing toilet room
Helm
- Demo existing toilet room
- Demo classrooms
American
- Demo existing toilet room
Phase 1 Project Scope
-
1 Story Building Addition & Sitework
-
8 Kindergarten Classrooms with Single User Toilets
-
2 Pre-K Classrooms with Single User Toilets
-
2 Multi-User Toilets (Boys & Girls)
-
2 Single User Toilets
-
1 Multipurpose Room (Storm Shelter)
-
Kitchen, Reading Room, OT/PT, Life Skills, Student Services & Lounge
-
2 Soft Play Surface Playgrounds
-
2 Storm Water Management Systems (East & West Parking Lots)
-
New Parking Lots & Driveways
-
Landscaping
What can we expect?
The construction at Westbrook will include a multi-purpose room addition and a two-classroom addition and existing classroom renovations for the District 34 Preschool program and full-day kindergarten.
In addition to the construction at Westbrook School there will be improvements in:
- Traffic flow
- ADA improvements
- Fire suppression sprinkler system throughout
- Site reconfiguration to address traffic flow and provide underground stormwater detention
- Storm shelter
- Classroom environment (acoustics, flooring, other)
Phase 1 Timeline
February 2021
March 2021
May 2021
- Ground Breaking (May 17, 2021
- Construction Commencement (pending permit approvals)
August 2022
Frequently Asked Questions
- When will construction start and end?
- Will construction workers be inside the school building?
- What if construction noise impacts the classroom?
- Will construction dust impact the air quality in the classroom?
- Will our current parking be affected by the construction?
- What do I do if I see a safety issue?
When will construction start and end?
Will construction workers be inside the school building?
What if construction noise impacts the classroom?
Will construction dust impact the air quality in the classroom?
Will our current parking be affected by the construction?
What do I do if I see a safety issue?
Contact your school principal or Director of Operations Steve Ruelli.